Phase 1 — Permits
Bygglov · startbesked · strandskydd · avlopp for the complement buildings.
Slutbesked (final approval)
pendingRequired before the buildings may be occupied. Submit on completion: confirmation that bygglov conditions were followed; facade photographs (all sides); chimney-sweep inspection protocol (fireplace, flue, roof safety); proof of approved sewage connection; any deviation approvals from the case officer.
Startbesked
issuedIssued — construction may legally proceed. Simplified kontrollplan for komplementbyggnader (enkla ärenden) confirmed in the startbesked.
Strandskydd (shoreline protection) dispensation
grantedThe property is inside the 100 m shoreline-protection zone. The 2022 application (Docs/KOMMUN/Bygglov/BygglovLKomp01.pdf) ticked "Helt ny byggnad alt. brygga", "Arbete i vatten", and "Trädfällning" — so the brygga was explicitly in scope alongside the new buildings. Dispens granted 2024-04-04. Decision document not saved locally — retrieve from Länsstyrelsen/Värmdö. Justification: area already built upon, access restricted from outside.
Bygglov (building permit)
approvedApproved: studio/gäststuga 35 m² BYA/BTA + 94 m² deck; bastu 11.3 m² BYA/BTA, 1 m roof overhang; fireplaces in both. Classified as komplementbyggnader — may NOT be used as independent dwellings.
Conditions (6)
- Buildings may not be occupied until slutbesked (final approval) is issued
- Studio must be connected to approved sewage before occupancy
- LOD (local stormwater management) required; separate WC and BDT sewage lines recommended
- Water-saving fixtures required
- Staking-out and position verification required
- Any deviation from the permit must be approved by the case officer before execution
Avlopp (sewage) permit
approvedLIVE. The original 2021-11-25 tillstånd (BMH 6015) never lapsed — Moderna Avlopp's June 2026 ansökan was handled as an ändring, and Värmdö kommun granted ändringstillstånd BMH 2447 (2026-07-03, same dnr) amending point 1.c to the new placement per the 2026-06-22 situationsplan, komplement- byggnad included; "i övrigt gäller beslutet i sin helhet". Valid five years from decision provided work starts within two years. Turn-key by Moderna Avlopp under Offer 5832 (approved 2026-06-22). Beslut received via Robin Lagerlöf 2026-07-16, acknowledged by Brett 2026-07-30. System: Ecobox Small minireningsverk, 5 PE / 750 L/day, Polynite phosphorus trap 500 kg, efterpoleringsbädd 6 m², 32 m from the drinking-water well per the approved situationsplan.
Conditions (5)
- Maximum 4-litre toilet flush; water-saving fixtures
- Professional installation; annual service by an approved technician
- Annual owner self-inspection; phosphorus filter replaced when pH drops below 9
- Annual sludge removal
- Nearest surface water: Långträsk (~55 m); drinking-water well 32 m per approved situationsplan
Decision PDFs under Phase 1 documents.