Phase 1 — Permits

Bygglov · startbesked · strandskydd · avlopp for the complement buildings.

Slutbesked (final approval)

pendingVärmdö kommun

Required before the buildings may be occupied. Submit on completion: confirmation that bygglov conditions were followed; facade photographs (all sides); chimney-sweep inspection protocol (fireplace, flue, roof safety); proof of approved sewage connection; any deviation approvals from the case officer.

Startbesked

issuedVärmdö kommun

Issued — construction may legally proceed. Simplified kontrollplan for komplementbyggnader (enkla ärenden) confirmed in the startbesked.

Case BYGG.2025.1705Granted 2025-05-27

Strandskydd (shoreline protection) dispensation

grantedLänsstyrelsen (County Administrative Board)

The property is inside the 100 m shoreline-protection zone. The 2022 application (Docs/KOMMUN/Bygglov/BygglovLKomp01.pdf) ticked "Helt ny byggnad alt. brygga", "Arbete i vatten", and "Trädfällning" — so the brygga was explicitly in scope alongside the new buildings. Dispens granted 2024-04-04. Decision document not saved locally — retrieve from Länsstyrelsen/Värmdö. Justification: area already built upon, access restricted from outside.

Granted 2024-04-04

Bygglov (building permit)

approvedVärmdö kommun

Approved: studio/gäststuga 35 m² BYA/BTA + 94 m² deck; bastu 11.3 m² BYA/BTA, 1 m roof overhang; fireplaces in both. Classified as komplementbyggnader — may NOT be used as independent dwellings.

Case BYGG.2025.1705Granted 2025-05-06Applicant Josefine Adner RichardsKA Robert Sandell (RISE cert C000334, valid to 2029-01-11)
Must start by May 2027 (2 yrs from legal force)Must complete by May 2030 (5 yrs from legal force)
Conditions (6)
  • Buildings may not be occupied until slutbesked (final approval) is issued
  • Studio must be connected to approved sewage before occupancy
  • LOD (local stormwater management) required; separate WC and BDT sewage lines recommended
  • Water-saving fixtures required
  • Staking-out and position verification required
  • Any deviation from the permit must be approved by the case officer before execution

Avlopp (sewage) permit

approvedVärmdö kommun — Bygg och Miljö

LIVE. The original 2021-11-25 tillstånd (BMH 6015) never lapsed — Moderna Avlopp's June 2026 ansökan was handled as an ändring, and Värmdö kommun granted ändringstillstånd BMH 2447 (2026-07-03, same dnr) amending point 1.c to the new placement per the 2026-06-22 situationsplan, komplement- byggnad included; "i övrigt gäller beslutet i sin helhet". Valid five years from decision provided work starts within two years. Turn-key by Moderna Avlopp under Offer 5832 (approved 2026-06-22). Beslut received via Robin Lagerlöf 2026-07-16, acknowledged by Brett 2026-07-30. System: Ecobox Small minireningsverk, 5 PE / 750 L/day, Polynite phosphorus trap 500 kg, efterpoleringsbädd 6 m², 32 m from the drinking-water well per the approved situationsplan.

Case MEA.2021.4441Ref BMH 2447 (ändringstillstånd; original tillstånd BMH 6015)Granted 2026-07-03
Conditions (5)
  • Maximum 4-litre toilet flush; water-saving fixtures
  • Professional installation; annual service by an approved technician
  • Annual owner self-inspection; phosphorus filter replaced when pH drops below 9
  • Annual sludge removal
  • Nearest surface water: Långträsk (~55 m); drinking-water well 32 m per approved situationsplan

Decision PDFs under Phase 1 documents.